Dam in Iraq at Full Operation for First
Time Since 1990
AFPS
BAGHDAD, Iraq
– With the completion of new transmission projects and the
rehabilitation of a turbine unit at Haditha Dam in Haditha, Iraq
last week, for the first time since 1990 all six turbines were
in full operation and the clean hydropower plant operated at full
capacity, generating 660 megawatts.
"The
incredible progress at Haditha is just one example of the huge
strides made by the U.S. Army Corps of Engineers and its partners
to increase the overall capacity of the Iraqi power system,"
said Army Maj. Gen. Ronald L. Johnson, commander of the corps'
Gulf Region Division. "Roland Shumate, our quality assurance
rep on site, working in close coordination with Iraqi engineers
and plant personnel, and our contractor, CH2MHill, have quickly
restored a capability at Haditha that had long been neglected
during the regime of Saddam Hussein."
Johnson said
work will continue as the plant personnel are trained to operate
and maintain the new equipment, switchgear and controls. "In
some cases, these technologies represent advances and efficiencies
enjoyed by those in the free world for the last 30 years, but
not seen before in Iraq," said Johnson.
The $12 million
project, administered by CH2MHill, and overseen by the Corps of
Engineers in support of the CPA and its Program Management Office,
began Feb. 6. At times it has employed more than 100 local Iraqi
workers, including those who had worked previously at the dam.
Previous projects
at Haditha included the restoration of transmission lines, under
contract with Washington Group International to link the hydropower
dam to the Iraqi power grid. Combined, an additional 460 megawatts
of capacity has been added to the overall national grid due to
the efforts of this partnering team, according to Robert Goss,
project manager for the Restore Iraqi Electricity Directorate
for the Corps of Engineers.
"Everyone
involved with this project did an outstanding job," said
Col. C. Kevin Williams, commander of the corps' Central District,
who executed the project. "From the contractor, the plant
personnel, our quality assurance guys, and the Marine and Azerbaijani
security forces on the ground - it was a tremendous team effort."
Stateside
Corps of Engineers expertise also was used to facilitate the shipment
of necessary parts and to provide technical assistance on site,
said Williams. Video teleconferencing systems and state-of-the-art
engineering tools allowed a virtual engineering team to assist
those living at the project site, working around the clock, to
restore the plant and provide added capacity to the national grid.
As part of
a nationwide effort, in part, by the Restore Iraqi Electricity
Directorate of the Gulf Region Division, Army engineers, soldiers
and civilians are working nonstop with contractors and Iraqi workers
to restore the dilapidated power infrastructure and improve the
quality of life for all of Iraq by increasing the available electricity,
officials said.
Repairing
damages from more than 30 years of neglect under Saddam, Corps
of Engineers teams are restoring transmission lines, improving
or replacing switching facilities and building or restoring more
than two dozen power generation projects to produce a capacity
never before seen in Iraq.